Powys Train Crash: Investigators release initial findings

Picture of Michael Holden

Share:

Powys Train Crash: Investigators release initial findings

Share:

Picture of Michael Holden

Share:

Talerddig collision
Talerddig collision // Credit: RAIB

The Rail Accident Investigation Branch has released its initial findings into the train crash in .

On Monday 21st October 2024, 1J25 18:31 to service collided with the 19:09 Machynlleth to Shrewsbury service just outside of Talerddig loop in Powys.

1 person died and four others were seriously injured in the collision, with 11 others needing hospital treatment.

Over the days after the collision, the RAIB worked to investigate the collision, before releasing the site and trains back to on Wednesday 23rd October.

The preliminary examination has found that 1J25 had been scheduled to stop at Talerddig loop to let 1S71 pass, and the driver of the train correctly applied service braking on the approach to the loop.

Talerddig collision
Talerddig collision // Credit: RAIB

However, after around 40 seconds after the first brake application, the On Train Data Recorder recorded an emergency brake demand being made.

This demand remained in place until the collision took place.

The RAIB says that there is conflicting evidence relating to the speed of the trains before impact but says initial analysis says that 1J25 was travelling at between 15 and 24 mph and 1S71 was travelling at around 6mph.

Investigations have found that at various locations on the approach to Talerddig loop, the rail adhesion levels were low, and an inspection of the sanding equipment fitted to 1J25 found the hoses to be blocked and unable to discharge sand.

The RAIB has therefore said that its full investigation will consider the following points:

  • the actions of those involved and any factors that may have influenced them
  • the level of wheel/rail adhesion present from the approach to Talerddig loop to the point of collision
  • the status and performance of the braking, wheel slide protection and sanding systems on train 1J25
  • the behaviour of both trains during and following the collision
  • Transport for ‘ policies relating to low wheel/rail adhesion and how it managed the risk of low adhesion on the Cambrian line
  • Network Rail’s policies relating to low wheel/rail adhesion and how it managed the risk of low adhesion on the Cambrian line
  • the processes used to assess and control the risk of overrun on the Cambrian line
  • any relevant underlying factors, including any actions taken in response to previous relevant safety recommendations.

Responses

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

  1. The maintenance on these units seems to be an issue. Not sure how the driver can effectively test the sanding system apart from an initial burst before departure. If there is muck of material which block the hoses later he/she can not foresee that. There have been issues with defective windscreen wipers too I am told.

  2. Brakes and sanders seem secondary. On a single track line, with a train ahead, surely a train switched into a loop would have the points set to prevent it leaving the loop until the oncoming train had passed? Can the digital signalling system decide which would be worse, a head on crash, or single train derailment??!

    1. If the rail conditions were so slippery that the train slid right through the loop, I would suggest that a more frequent railhead treatment regime would have helped. If trees are going to be allowed to flourish close to railways, no amount of emergency sanding equipment maintained on a train will be adequate.

  3. From what I have heard from the radio report that after a normal brake application it had just slide down the line, the sanding equipment was not kept in working order and when an emergency brake application was applied it just carried on sliding and the ‘Anti Lock’ system was useless. It looks like the driver was not at fault here but the blame should be put on these that fail to keep the equipment working, although it should be noted that the driver should check that the preparation of the train has been carried out.

  4. It sounds from initial findings that the TPWS intervened when the west bound train failed to stop in Talerddig loop. The potential downside with this intervention is it is an emergency brake intervention which is not helpful when train is already sliding on the rails. There would be little the driver could do when this happened.

  5. One would suggest some on board monitoring equipment during low/poor rail adhesion conditions to the stock, and instructive training for drivers on how to regain braking control Stock allowing?

  6. I presume the up train was in the loop under a red signal, if this were the case surely the down train would have passed by, the points being set correctly for this. I expect I may have missed something on this.

    1. The up train never got as far as the loop. The Down train slipped through the loop and out of the other end onto the single line. There are no lineside signals as the trains on that line have in-cab signalling.

Related Articles