Rail upgrades completed in London, Macclesfield, Carlisle and Warrington free up Jubilee Weekend

Picture of Chloe White

Share:

Rail upgrades completed in London, Macclesfield, Carlisle and Warrington free up Jubilee Weekend

Share:

Picture of Chloe White

Share:

Watford Junction track upgrades bulldozers and whackers May 2022
Credit: Network Rail

Network Rail’s essential upgrade works, which were carried out over the Early May Bank holiday between , the and North West, are now complete

A range of essential upgrades was carried out during the bank holiday weekend and followed on from work which took place over the Easter period and has now seen £41.1m invested in the North West and Central regions as part of Network Rail’s ongoing commitment to improving passenger and freight services moving into the future.

Engineers installing new railway signal posts Macclesfield May 2022
Credit: Network Rail

Both periods of work saw a complete closure for London Euston station which underwent vital track upgrades at Watford and Wembley.

Work carried out between Saturday the 30th of April and Monday the 2nd of May also saw:

  • Railway drainage work in that will protect the tracks from future flooding
  • Demolition of an old railway viaduct in Birmingham in preparation for the HS2 (SAS 13) bridge renewal this weekend
  • has been upgraded in Macclesfield
  • Bridge upgrade work was carried out in
  • Track foundation strengthening took place in Warrington and Carlisle
  • Track replacement took place on the West Coast main line in Carstairs in Scotland

Network Rail teams have carried out as much work as possible over the two bank holidays in order for the West Coast main line to be fully open in time for the Queen’s Platinum Jubilee which will take place between the 2nd and 5th of June.

Old signalling gangtry lifted out by crane Macclesfield May 2022
Credit: Network Rail

Services returned to normal on Tuesday the 3rd of May and Network Rail wishes to thank passengers for their patience.

SAS 13 bridge demolition work
Credit: Network Rail

Tim Shoveller, managing director for Network Rail’s North West and Central region, said: “I’m extremely proud of the hundreds of workers and contractors who’ve pulled out all the stops over the last two bank holidays to improve the railway for the future.

“I’d like to thank passengers whose travel has been disrupted by our £41.1m upgrades over Easter and Early May. The great news is the West Coast main line and major routes in the Midlands and North West are now in the best possible shape for the Platinum Jubilee weekend when the whole country will join in to celebrate 70 years of our Queen on the throne.”

SAS 13 bridge demolition work before
Credit: Network Rail

The railway is expected to be busy during the major national event and passengers are advised to plan their travel ahead via http://www.nationalrail.co.uk