Ffestiniog Railway completes 8 month overhaul of steam locomotive Lyd

Picture of Michael Holden

Share:

Ffestiniog Railway completes 8 month overhaul of steam locomotive Lyd

Share:

Picture of Michael Holden

Share:

Lyd in steam on a PTG Tour on the Ffestiniog and Welsh Highland Railway
Credit: Chris Parry

Many readers might be reading the title and thinking “Has Lyd really been in service for 10 years?!”, and you’d be right in questioning yourself.

However, Lyd was withdrawn from service in May 2020 after being used regularly over the last ten years on the , as well as stints on the Welsh Highland Railway.

The overhaul, due to COVID, didn’t start until October 2020 and work started at pace, with teams divided into two to work on the chassis and boiler.

Only a retube was needed on the boiler as it had only been in service for 10 years.

Chassis work for Lyd meant removing the cylinders as the port faces were reconditioned due to problems with lubrication.

The rear pony truck was modified to allow a side discharging ash pan to be fitted instead of the originally fitted end discharging pan.

Lyd in steam on a PTG Tour on the Ffestiniog and Welsh Highland Railway
Credit: Chris Parry

At the Lynton and Barnstaple Railway, the loco ash was discharged into an ash pit, but at the Ffestiniog Railway, these pits do not exist and ash is discharged into a wheelbarrow.

The brake gear has been modified to run down the centre of the chassis to give clearance for the new ash pan, and a new loco brake control has been fitted to allow Lyd’s loco vacuum brake to be operated while the rest of the train has full vacuum. This removes the need for crews to have to wind the handbrake on at every station stop.

Lyd in steam on a PTG Tour on the Ffestiniog and Welsh Highland Railway
Credit: Chris Parry

Overhaul work was completed and Lyd was tested in May 2021. After a shakedown process, the locomotive has been in service on both the Ffestiniog and Welsh Highland Railways.

The locomotive will keep its Southern Railway livery for the foreseeable future.

Festiniog Railway General Manager Paul Lewin said: “I am particularly pleased with the Boston Lodge staff completing the overhaul so quickly considering that it involved the removal and re-installation of the boiler and cylinders”.

Where Next?

RAILADVENT NEWS
The latest railway news
RailAdvent Plus
Discounts, videos, pictures and more!
FREE NEWSLETTERS
Signup to our daily and weekly newsletters
RAILADVENT SHOP
Railway Prints, DVD’s / Blu-Ray’s, books and more
LOCOSTOP COMMUNITY
Come and share your railway pictures
UK STEAM INFO
Upcoming mainline steam tours/loco movements
Ffestiniog Railway
Visit their website

Responses

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Related Articles