The LMS Patriot Project has released a short update on what has been happening in April.
April was a difficult month for the project, whilst weld repairs were being completed at Riley and Son, a significant crack was found on one of the trailing wheel pans.
Repairs on this started at the end of March, but the cracking was found to be more serious than first thought and after inspection, it was been decided that the wheel will be scrapped and the five other driving wheels will be tested for cracks.
More bad news came in April as the LMS Patriot Project was told that the material for the axle replacement from South Africa is now not expected until Autumn 2022 as a result of the coronavirus pandemic.
Alternative suppliers are being looked into as a result of the long lead time.
Work has reduced at West Shed as 6233 Duchess of Sutherland is worked on in preparation for her return to mainline duties in 2021. However, work has progressed on the expansion link trunnions.
If you would like to become a member of the LMS Patriot Project or to donate towards the construction of 5551 The Unknown Warrior, please visit the LMS Patriot Project website.
Where Next?
RAILADVENT NEWS
The latest railway news
FREE NEWSLETTERS
Signup to our daily and weekly newsletters
RAILADVENT SHOP
Prints, DVD’s, Clocks, Mouse Mats and more!
COMPETITION TIME
Enter our latest competition
UK STEAM INFO
Upcoming mainline steam tours/loco movements
LMS-Patriot Project
Visit their website
Responses