First London Underground trains run on new Northern Line extension to Battersea

Picture of Michael Holden

Share:

First London Underground trains run on new Northern Line extension to Battersea

Share:

Picture of Michael Holden

Share:

Test train on the Northern Line at Nine Elms
Credit: Transport for London

Transport for London has confirmed that a major milestone was met at Christmas as a test passenger train travelled through the new tunnels, on the extension, from to Power Station.

On arrival at Battersea, the train used the new crossover junction to complete its return journey back to Kennington.

The first test journey marks the completion of major work on the Northern Line extension, which includes:

  • Switching on electricity supply to the new stations at Battersea Power Station and Nine Elms.
  • Energising the power supply to the tracks, allowing trains to run on the new section.
  • Signalling software connecting the extension to the network at Kennington has been commissioned.
Test train on the Northern Line at Nine Elms
Credit:
Work on the Northern Line extension remains on track to be completed in Autumn 2021 and is now focussing on the signalling upgrades needed and fitting out at the two new stations.

Heidi Alexander, Deputy Mayor for Transport, said: “I’m delighted that the Northern Line Extension has reached this major milestone, with the project on track to welcome its first passengers in the autumn. Last year was one of the hardest in TfL’s history so it’s great to start 2021 on a positive footing, not least because the extension will support thousands of new jobs and homes for our city.”

Stuart Harvey, TfL’s Director of Major Projects, said: “Seeing a Northern line train travelling through the extension for the first time is a really significant milestone and demonstrates the commitment of our brilliant team who have been working so hard during such a challenging year.  The Northern Line Extension continues to support jobs, homes and growth in this exciting riverside destination and has created employment through the supply chain across the UK. We are now focused on making sure the signalling software and systems are ready along with completing the final stages of fit-out of the two new stations before the planned opening of the extension in the autumn.”

Where Next?

RailAdvent Plus
Support the website and get benefits in return
RailAdvent News
The latest railway news
RailAdvent Shop
Railway Prints, DVD’s / Blu-Ray’s and more
LocoStop Community
Come and share your railway pictures
Mainline UK Steam Info
Upcoming mainline steam tours/loco movements
Transport for London
Visit their website

Responses

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

  1. Maybe rename Battersea Power Station to New Battersea, East Battersea or Battersea Riverside. And in future to extend the Northern Line to Clapham Junction.

Related Articles