South London trains set to be disrupted

Picture of Roger Smith

Share:

South London trains set to be disrupted

Share:

Picture of Roger Smith

Share:

Engineers working on resignalling works in SOuth London. // Credit Network Rail
Engineers working on resignalling works in SOuth London. // Credit Network Rail

Train services will be suspended for one week at the end of October on parts of National Rail and London Overground lines in South London because of improvements being made to the signalling,

The disruption will be during the half-term week from Saturday, 26 October to Friday 1 November.

During the closure, passengers on services between Herne Hill, Wimbledon and Sutton should use London Buses or alternative National Rail, London Trams, or London Underground routes.

[NWR] Kent and South East London railway renewed
Track being relaid in South London. // Credit: Network Rail

National Rail service alterations

Saturday 26 and Sunday 27 October

  • There will be no Southern services between:
  • and London Bridge;
  • London Victoria and West Croydon (via );
  • London Bridge and Streatham.
  • London Bridge and Beckenham Junction.
  • Replacement buses will operate between London Bridge and Streatham Common, via Peckham Rye and Tulse Hill.
  • On all other routes, local London Buses will accept paper train tickets.

Monday 28 October to Friday 1 November

  • No trains will run between London Bridge and Streatham or London Bridge and Beckenham Junction.
  • London Bridge to London Victoria, and London Victoria to West Croydon (via Crystal Place) services will only run between London Victoria and .
  • Extra trains will run between London Bridge and Sutton via West Croydon.
  • Replacement buses will operate between London Bridge and Streatham Common, via Peckham Rye and Tulse Hill.
  • On all other routes, local London Buses will accept paper train tickets.
Feltham to Wokingham resignalling
Network Railr resignalling work. // Credit: Network Rail

London Overground

Saturday 26 October to Friday 1 November

  • Services between Surrey Quays and Clapham Junction will be replaced by buses.

Saturday 26 to Tuesday 29 October

  • There will be no trains between Sydenham and Crystal Palace.
  • Passengers travelling to and from Crystal Palace should use local buses.

Saturday 26 to Tuesday 29 October

  • An amended service will operate between:
  • Highbury & Islington;
  • West Croydon and .

30 October to Friday 1 November

  • Some Crystal Palace and New Cross services will be re-timed.

Signalling improvements to the lines in South London were due to take place in February but were delayed pending further changes.

At the end of last month, services were disrupted for ten days due to work at Crystal Palace Junction.

Track replacement at Crystal Palace
Crystal Palace Junction where track replacement took place last month // Credit: Network Rail

“It vital that we continue to invest to modernise our assets and give passengers the delay free journeys they expect.

“Signalling upgrades between East Croydon and London Victoria in 2022 saw delays cut by more than half and we are expecting this phase of signalling upgrades in the Crystal Palace, Tulse Hill and Peckham Rye areas to deliver a similarly impressive reduction in delays when it comes into use.

“We know the work means days of major changes to journeys for passengers and we are sorry for the disruption.?Please plan ahead, look out for further updates and follow travel advice.”

Lucy McAuliffe, Network Rail Sussex route director

“While this major investment in modern signalling is inevitably disruptive, earlier phases of Network Rail’s programme have already brought huge punctuality improvements for our customers on other South London routes. We thank passengers in advance for their patience and understanding while the work is under way.”

Jenny Saunders, Govia Thameslink Railway Customer Services Director

Responses

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Related Articles