Tyne Valley and Settle & Carlisle rail routes reopen for services

Picture of Roger Smith

Share:

Tyne Valley and Settle & Carlisle rail routes reopen for services

Share:

Picture of Roger Smith

Share:

Northern train passing over repaired Petteril Bridge junction with B&Q in background
Northern train passing over repaired Petteril Bridge junction with B&Q in background // Credit: Network Rail

After services on two key rail routes in had been disrupted for seven weeks, since 6.00am yesterday morning, Wednesday, 7th December, direct trains are running again on the Tyne Valley line between Carlisle and and the Settle to Carlisle line between Carlisle, and Skipton.

On Wednesday, 19th October, a train carrying powdered cement was derailed at Petteril Bridge junction, just outside Carlisle. Since then, Network Rail engineers have been working around the clock to restore services.

Northern service passing over repaired Petteril Bridge Junction (2)
service passing over repaired Petteril Bridge Junction. // Credit: Network Rail

The derailment caused extensive damage to a Victorian-built railway bridge, railway lines, and equipment. Over 25,000 hours of work went into restoring the railway so trains can run again.

Cement being removed from derailed freight wagons in Carlisle
Cement being removed from the derailed freight wagons. // Credit: Network Rail

Drone footage shows work taking place to restore services over the bridge.

Work to get the line open again included:

  • recovering the locomotive and 11 of the 14 wagons involved in the derailment;
  • using a giant vacuum to remove 80 tonnes of powdered cement from three wagons that needed recovery by crane;
  • replacing 80 metres of damaged track;
  • installing 400 metres of new cables for signals and points;
  • replacing two points switches;
  • pouring 125 tonnes of concrete into metal reinforcement cages used to repair the damaged bridge.
Aerial shot of new bridge deck in Carlisle after freight derailment (2)
Aerial shot of the new bridge deck. // Credit: Network Rail

Mark Evans, Network Rail senior programme manager, said: “I’d like to thank passengers for their patience while we worked tirelessly to get the railway back up and running after it was severely damaged by the freight train derailment.

“This has been a very complex recovery and repair job. Now it’s complete this major railway junction is future-proofed and has been strengthened in the very rare event anything like this should happen again meaning more reliable journeys for passengers and freight for years to come.”

Kerry Peters, regional director at Northern, said: “We have been working very hard with Network Rail to reopen the railway at Petteril bridge following the freight train derailment in October.

“Now that work is complete, Northern services have resumed on both the Tyne Valley and Settle to Carlisle lines – and we have allocated extra advance purchase fares to welcome people back on-board. We’d like to thank our customers for being patient during this disruption and everyone involved in getting our passengers moving again.”