Update on New-Build Standard 3 Tank 82045 steam locomotive – May 2019

Picture of Jamie Duggan

Share:

Update on New-Build Standard 3 Tank 82045 steam locomotive – May 2019

Share:

Picture of Jamie Duggan

Share:

82045 Inside Erection Shop // Credit Jim Norman
82045 Inside Erection Shop // Credit Jim Norman

May brought good news for the Trust, along with more progress on building 82045 at the Severn Valley Railway.

Undercover

Some time in May, 82045 was moved into Bridgnorth’s erection shop as a space had become available.

Although not on a permanent basis, the Trust hopes to complete the ‘bottom-end’ of the tank while inside the shop and is protected from the elements. This of course depends on how much support the Trust receives.

A few components are currently under construction/receiving work by contractors. These are the four axleboxes for both trucks, which are being white metalled by Osborne Engineering, and both the union links, combination levers & pull rod have been forged by Stephenson Engineering.

The next task by this company is to complete the reversing shaft.

Forged Items // Credit Robert Stephenson
Forged Items // Credit Robert Stephenson

Work on building the steam chest cladding and fitting the vacuum pipework is in progress, along with machining a few parts, such as piston rods.

For more information or to support , please visit their website here.

Where Next?

News Homepage
   For the Latest Railway News
RailAdvent Online Shop
   Framed Prints, DVD’s / Blu-Ray’s and more
LocoStop Community
   Come and share your railway pictures

Responses

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Related Articles